Key information
Overview
The purpose of the project is In-Line Inspection (ILI) for pipeline technical condition assessment prior to the transition from natural gas (NG) to hydrogen operation.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Bekanntmachungs-ID: CXVHYH0DYYD6T4L4# Contract award on the initial offer: The contracting authority may award the contract on the basis of the initial tender without conducting negotiations. The decision on this matter is at the discretion of the contracting authority in accordance with the tender documents. Further information can be found in the tender documents. Combination of lots: Tenders may be submitted for several lots. The contracting authority reserves the right to award such combined tenders as a single contract, provided that this is economically viable in accordance with the objective and non-discriminatory criteria set out in the tender documents. Further information can be found in the tender documents.
For the pipeline sections 1 to 3 mechanical cleaning using i.e. bi-directional cleaning pigs is considered. Four (4) cleaning pig runs shall be assumed to be required per pipeline section. For the very first cleaning pig run per section a bi-directional pig must be offered which shall proof pig passage by either mechanical or intelligent gauge plate(s).
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 32-in (DN 800) pipeline sections are considered: Section 1 Outer diameter (mm): 813 Length (km): 57 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 2 Outer diameter (mm): 813 Length (km): 158 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 3 Outer diameter (mm): 813 Length (km): 210 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days, calculated from two (2) days after tool receive and acceptance of the run, shall be considered for reporting: Section 1 Data quality report: 10 Preliminary report: 30 Final report: 40 Section 2 Data quality report: 10 Preliminary report: 30 Final report: 60 Section 3 Data quality report: 10 Preliminary report: 30 Final report: 60 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
For the pipeline sections 1 to 3 mapping of the pipeline is considered over the entire section or a to be determined sub-section of it. A minimum of twenty (20) AGMs must be provided per section. Inertial measurement data are considered for bending strain analysis which shall be offered as a combined service. For the pipeline sections 1 to 3 the following pipeline anomalies shall be addressed by ILI technologies:
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 32-in (DN 800) pipeline sections are considered: Section 1 Outer diameter (mm): 813 Length (km): 57 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 2 Outer diameter (mm): 813 Length (km): 158 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 3 Outer diameter (mm): 813 Length (km): 210 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days, calculated from two (2) days after tool receive and acceptance of the run, shall be considered for reporting: Section 1 Data quality report: 10 Preliminary report: 30 Final report: 40 Section 2 Data quality report: 10 Preliminary report: 30 Final report: 60 Section 3 Data quality report: 10 Preliminary report: 30 Final report: 60 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider internal and external metal-loss detection and sizing in straight pipe, field- and hot-bends. In case a combination of ILI technologies implemented on one or more ILI tools which enable a combined data analysis leading to a superior perfor-mance compared to individual ILI technologies, the technologies shall be offered as a com-bined service and shall be emphasized as such.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 32-in (DN 800) pipeline sections are considered: Section 1 Outer diameter (mm): 813 Length (km): 57 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 2 Outer diameter (mm): 813 Length (km): 158 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 3 Outer diameter (mm): 813 Length (km): 210 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days, calculated from two (2) days after tool receive and acceptance of the run, shall be considered for reporting: Section 1 Data quality report: 10 Preliminary report: 30 Final report: 40 Section 2 Data quality report: 10 Preliminary report: 30 Final report: 60 Section 3 Data quality report: 10 Preliminary report: 30 Final report: 60 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider detection and sizing of geometric deviations from the norm of straight pipe and in bends.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 32-in (DN 800) pipeline sections are considered: Section 1 Outer diameter (mm): 813 Length (km): 57 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 2 Outer diameter (mm): 813 Length (km): 158 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 3 Outer diameter (mm): 813 Length (km): 210 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days, calculated from two (2) days after tool receive and acceptance of the run, shall be considered for reporting: Section 1 Data quality report: 10 Preliminary report: 30 Final report: 40 Section 2 Data quality report: 10 Preliminary report: 30 Final report: 60 Section 3 Data quality report: 10 Preliminary report: 30 Final report: 60 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider detection and sizing of axially oriented crack and crack-like anomalies. The definition of terms is according to the publicly available Pipeline Operators Forum Recommended Practice POF 100 edition 2021.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 32-in (DN 800) pipeline sections are considered: Section 1 Outer diameter (mm): 813 Length (km): 57 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 2 Outer diameter (mm): 813 Length (km): 158 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 3 Outer diameter (mm): 813 Length (km): 210 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days, calculated from two (2) days after tool receive and acceptance of the run, shall be considered for reporting: Section 1 Data quality report: 10 Preliminary report: 30 Final report: 40 Section 2 Data quality report: 10 Preliminary report: 30 Final report: 60 Section 3 Data quality report: 10 Preliminary report: 30 Final report: 60 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider detection and sizing of localized variations of the pipe materi-al hardness with respect to the mean material hardness per joint and exceeding an upper and lower bound threshold depending on the offered tool performance.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 32-in (DN 800) pipeline sections are considered: Section 1 Outer diameter (mm): 813 Length (km): 57 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 2 Outer diameter (mm): 813 Length (km): 158 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 3 Outer diameter (mm): 813 Length (km): 210 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days, calculated from two (2) days after tool receive and acceptance of the run, shall be considered for reporting: Section 1 Data quality report: 10 Preliminary report: 30 Final report: 40 Section 2 Data quality report: 10 Preliminary report: 30 Final report: 60 Section 3 Data quality report: 10 Preliminary report: 30 Final report: 60 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider detection of pipe material yield strength variation per joint with respect to available pipe material records per joint.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 32-in (DN 800) pipeline sections are considered: Section 1 Outer diameter (mm): 813 Length (km): 57 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 2 Outer diameter (mm): 813 Length (km): 158 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 3 Outer diameter (mm): 813 Length (km): 210 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days, calculated from two (2) days after tool receive and acceptance of the run, shall be considered for reporting: Section 1 Data quality report: 10 Preliminary report: 30 Final report: 40 Section 2 Data quality report: 10 Preliminary report: 30 Final report: 60 Section 3 Data quality report: 10 Preliminary report: 30 Final report: 60 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider measurement of the axial strain along the entire section lengths. The service shall be offered as a combined service of ILI, strain-based Fitness-For-Service assessment and, if possible, a total strain assessment including bending strain as-sessment results (see Lot 2). Pipe samples and pipe sample data can be provided upfront if needed to enhance the offered performance.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 32-in (DN 800) pipeline sections are considered: Section 1 Outer diameter (mm): 813 Length (km): 57 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 2 Outer diameter (mm): 813 Length (km): 158 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Section 3 Outer diameter (mm): 813 Length (km): 210 Nominal pipe wall thickness (mm): 11.9 Pipe material: StE 480.7 TM Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days, calculated from two (2) days after tool receive and acceptance of the run, shall be considered for reporting: Section 1 Data quality report: 10 Preliminary report: 30 Final report: 40 Section 2 Data quality report: 10 Preliminary report: 30 Final report: 60 Section 3 Data quality report: 10 Preliminary report: 30 Final report: 60 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
For pipeline section 4 mechanical cleaning using i.e. bi-directional cleaning pigs is consid-ered. Four (4) cleaning pig runs shall be assumed to be required per pipeline section. For the very first cleaning pig run per section a bi-directional pig must be offered which shall proof pig passage by either mechanical or intelligent gauge plate(s).
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 40-in (DN 1000) pipeline section is considered: Section 4 Outer diameter (mm): 1016 Length (km): 97 Nominal pipe wall thickness (mm): 14.6 Pipe material: L 485 MB Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days from two (2) days after tool receive and acceptance of the run shall be considered for reporting: Section 4 Data quality report: 10 Preliminary report: 30 Final report: 40 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
For pipeline section 4 mapping the pipeline is considered over the entire section or a to be determined sub-section of it. A minimum of twenty (20) AGMs must be provided. Inertial measurement data are considered for bending strain analysis which shall be offered as a combined service.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 40-in (DN 1000) pipeline section is considered: Section 4 Outer diameter (mm): 1016 Length (km): 97 Nominal pipe wall thickness (mm): 14.6 Pipe material: L 485 MB Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days from two (2) days after tool receive and acceptance of the run shall be considered for reporting: Section 4 Data quality report: 10 Preliminary report: 30 Final report: 40 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider internal and external metal-loss detection and sizing in straight pipe, field- and hot-bends. In case a combination of ILI technologies implemented on one or more ILI tools which enable a combined data analysis leading to a superior perfor-mance compared to individual ILI technologies, the technologies shall be offered as a com-bined service and shall be emphasized as such.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 40-in (DN 1000) pipeline section is considered: Section 4 Outer diameter (mm): 1016 Length (km): 97 Nominal pipe wall thickness (mm): 14.6 Pipe material: L 485 MB Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days from two (2) days after tool receive and acceptance of the run shall be considered for reporting: Section 4 Data quality report: 10 Preliminary report: 30 Final report: 40 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider detection and sizing of geometric deviations from the norm of straight pipe and in bends.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 40-in (DN 1000) pipeline section is considered: Section 4 Outer diameter (mm): 1016 Length (km): 97 Nominal pipe wall thickness (mm): 14.6 Pipe material: L 485 MB Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days from two (2) days after tool receive and acceptance of the run shall be considered for reporting: Section 4 Data quality report: 10 Preliminary report: 30 Final report: 40 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider detection and sizing of axially oriented crack and crack-like anomalies. The definition of terms is according to the publicly available Pipeline Operators Forum Recommended Practice POF 100 edition 2021.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 40-in (DN 1000) pipeline section is considered: Section 4 Outer diameter (mm): 1016 Length (km): 97 Nominal pipe wall thickness (mm): 14.6 Pipe material: L 485 MB Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days from two (2) days after tool receive and acceptance of the run shall be considered for reporting: Section 4 Data quality report: 10 Preliminary report: 30 Final report: 40 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider detection and sizing of localized variations of the pipe materi-al hardness with respect to the mean material hardness per joint and exceeding an upper and lower bound threshold depending on the offered tool performance.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 40-in (DN 1000) pipeline section is considered: Section 4 Outer diameter (mm): 1016 Length (km): 97 Nominal pipe wall thickness (mm): 14.6 Pipe material: L 485 MB Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days from two (2) days after tool receive and acceptance of the run shall be considered for reporting: Section 4 Data quality report: 10 Preliminary report: 30 Final report: 40 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider detection of pipe material yield strength variation per joint with respect to available pipe material records per joint.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 40-in (DN 1000) pipeline section is considered: Section 4 Outer diameter (mm): 1016 Length (km): 97 Nominal pipe wall thickness (mm): 14.6 Pipe material: L 485 MB Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days from two (2) days after tool receive and acceptance of the run shall be considered for reporting: Section 4 Data quality report: 10 Preliminary report: 30 Final report: 40 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.
Offered services shall consider measurement of the axial strain along the entire section lengths. The service shall be offered as a combined service of ILI, strain-based Fitness-For-Service assessment and, if possible, a total strain assessment including bending strain as-sessment results (see Lot 10). Pipe samples and pipe sample data can be provided upfront if needed to enhance the offered performance.
The ILI service is being carried out along the STEGAL and MIDAL Süd pipelines., Fulda, Germany
#Besonders auch geeignet für:other-sme# The following NPS 40-in (DN 1000) pipeline section is considered: Section 4 Outer diameter (mm): 1016 Length (km): 97 Nominal pipe wall thickness (mm): 14.6 Pipe material: L 485 MB Primary factory weld type: Longitudinal Weld type: DSAW Min. bend radius: ? 3 × D Max. bend curvature (degrees): 90 ILI NG operating pressure (bar): 50 ? OP ? 80 ILI NG velocity (m/s): 0.5 ? v ? 4 Location launch/receive site: Germany, onshore Reporting timeline The following number of working days from two (2) days after tool receive and acceptance of the run shall be considered for reporting: Section 4 Data quality report: 10 Preliminary report: 30 Final report: 40 In case the above-mentioned reporting timelines cannot be met, the most expedited reporting schedule shall be offered and parameters influencing the offered schedule must be stated.